When to bring in the hardwood flooring contractor
Bring us in when the plans are drawn and the flooring allowance is being set, before framing if possible. At that point we can flag the things that change the floor. A slab on grade main level or radiant heat means engineered. Plank direction relative to the joists and the main sight line is easier to settle on paper than on the day.
What the house needs before hardwood is delivered
Before wood is delivered the house has to be closed in, the HVAC running at living conditions, and the wet trades done. Drywall is dry, and primer and the first coat of wall paint are on. We take moisture readings in the subfloor and in the wood on delivery, and we start once the two are close. In a dried-out winter house that can be a few days.
Where hardwood flooring falls among the other trades
Our preferred sequence is floor installed before cabinets, so the plank runs under the toe kicks and a future kitchen remodel does not leave a hole in the floor. The other trades then work on top of a covered floor. On a site-finished job, sanding and finishing happen after the painters have put their final coat on the walls and ceilings, so floor finish is one of the last things in the house.
Finish samples with the homeowner, and stairs
We make sample boards from the species, cut and width specified for the job and bring them to the house once there is daylight coming through the windows. The homeowner, the designer and Burton look at them in the room where they will live. Stair treads and nosings are milled from the same oak as the floor and finished with the same system, so the color is one color.
Builder questions about hardwood flooring
What does a spec sheet need to include?
Species, cut, grade, width, construction, finish system, sheen, pattern and direction, transitions and stairs. A designer can hand us a sheet with those lines filled in, and we will fill in whatever is left open and send it back for sign-off.
Can you install prefinished if the closing date is tight?
Yes. We install prefinished white oak as well as site-finished, and prefinished takes the sanding and cure days out of the schedule. Our white oak guide lays out the difference so the homeowner can decide.
Do you protect the floor while the other trades finish?
Yes. After installation and before finish, the floor is covered with breathable paper and hardboard in the traffic lanes, and we ask that trades stay off the uncovered areas. After the final coat, foot traffic in socks is fine after a day.